AN OPTIMIZATION-BASED APPROACH FOR MITIGATING THE FERRANTI EFFECT THROUGH OPTIMAL SELECTION AND PLACEMENT OF SHUNT REACTORS IN LONG-DISTANCE TRANSMISSION LINES
Abstract: long-distance high-voltage transmission lines (e.g. 138 kV over 300 km) can exhibit the Ferranti effect, wherein the receiving-end voltage rises above the sending-end voltage under light or no-load conditions. This overvoltage arises from the line’s distributed capacitance charging current interacting with its inductance, posing risks of insulation stress and instability. Traditional mitigation involves shunt reactors, but optimal sizing and siting require systematic analysis.Approach: We formulate a multi-objective optimization to place fixed shunt reactors on a real 138 kV, 300 km line. Objectives include minimizing a voltage stability index, reducing reactive power losses, and limiting voltage deviation from nominal. Constraints enforce power-flow balance and equipment limits. The line is modeled with a nominal π-equivalent, capturing Ferranti rise and reactive flows. We implement two heuristic optimizers—Particle Swarm Optimization (PSO) and a standard Genetic Algorithm (GA)—in MATLAB to determine optimal reactor locations and sizes.Results: An ETAP simulation of the 138 kV/300 km line shows a base-case Ferranti rise of ~5%. Placing a single 50 MVAr shunt reactor at the midpoint, or splitting 25+25 MVAr at the ends, substantially reduces the overvoltage. Both PSO and GA identify similar solutions (e.g. ~40–45 MVAr at ~120–160 km from the sending end) that bring the receiving voltage within ±1% of nominal. PSO converges faster (≈50–60 iterations) than GA (≈80–100 generations) while achieving slightly better or comparable objective values. Voltage profiles and loss metrics (Table I) confirm that the optimized reactors stabilize the system.Conclusion/Recommendations: Switched or fixed shunt reactors optimally placed can effectively mitigate the Ferranti effect in long lines. The PSO-based design procedure proved computationally efficient and accurate for the 138 kV case. In practice, we recommend installing a mid-line reactor or divided reactors to balance voltage, with tuning by PSO-like methods. Careful consideration of cost vs. performance and sensitivity (e.g. to load changes) is necessary. Future work may integrate FACTS devices or adaptive control for dynamic compensation.
Keywords: Ferranti effect, long transmission lines, shunt reactor placement, particle swarm optimization, genetic algorithm.
https://doi.org/10.24412/2712-8849-2025-1091-664-680
Introduction. In lightly-loaded or open-circuited long transmission lines, the receiving-end voltage can exceed the sending-end voltage, a phenomenon known as the Ferranti effect. Discovered in the 19th century, the Ferranti effect arises because the line’s shunt capacitance injects a leading (capacitive) current that produces an in-phase voltage drop across the line inductance. Intuitively, the line charging current flows without significant load draw, raising the remote-end voltage. This effect is more pronounced in longer lines – for example, studies show that a 300 km, 50 Hz line can have a 5–40% voltage rise. In one simulated 500 kV, 300 km case, the receiving-end voltage was ~40% higher than the sending-end due to capacitive charging. In practical terms, excessive Ferranti rise can exceed statutory voltage limits, endangering equipment and causing instability.Shunt reactors are a classical remedy: large inductors connected (usually at line ends) that absorb excess reactive power and clamp voltage. Shunt reactors regulate the reactive power balance and prevent “capacitive rise”. In fact, Southern States notes that reactors “are applied to regulate the reactive power balance of a system by compensating for the surplus reactive power generation of transmission lines” and to control voltage rise caused by the Ferranti effect. For very long lines operating well below their surge-impedance loading (SIL), reactors may even be permanently switched in. However, simply adding reactors can introduce complexity: oversizing wastes money, while mislocation can produce suboptimal voltage profiles. Furthermore, multiple objectives (voltage stability, losses, voltage deviation, cost) must be balanced.Motivated by these challenges, this work focuses on an optimization-based design for shunt reactors on a real 138 kV, 300 km system. Unlike many studies using standard IEEE test cases, we consider parameters representative of an actual transmission corridor. We use modern heuristic algorithms (PSO and GA) to search for the best reactor placements and ratings. PSO, introduced by Kennedy and Eberhart, models a population of “particles” exploring the solution space, while GA mimics biological evolution through selection, crossover, and mutation. Both have been applied to power-system problems, but here we tailor them to the Ferranti mitigation problem. Our objective is to reduce the Ferranti-induced overvoltage below acceptable limits and optimize related metrics (e.g., minimize losses and voltage deviations) while respecting operational constraints[1].This paper is organized as follows: We first formalize the objectives and constraints of the optimization problem. We then present the mathematical models: the π-equivalent line capturing Ferranti effect, and the shunt-reactor injection model. The next section describes the PSO and GA algorithms used, along with our MATLAB implementation. In the Results section, we apply the approach to the 138 kV line using ETAP simulations, compare single vs. split reactor solutions, and contrast PSO vs. GA outcomes. A Discussion interprets the findings, addressing feasibility and sensitivity. Finally, we summarize conclusions and practical recommendations.Figure 1. Ferranti Effect ETAP simulation model.Objective Functions.The optimization is multi-objective, balancing system security and efficiency. Our main objectives include:Voltage Stability Index (VSI): A scalar measure reflecting proximity to voltage collapse. For example, one may use the Kessel L-index or Fast Voltage Stability Index. In this work, we minimize the maximum of such indices across load buses.
Acknowledgments:
The authors would like to acknowledge Sakarya University.
Mammadov Ibrahim would like to express his special thanks to his girlfriend, Fidan Gafarova,
for being by his side and supporting him during this stressful period.
Полная версия статьи PDF
Номер журнала «Вестник науки» № 10 (91) том 2
Ссылка для цитирования:
AN OPTIMIZATION-BASED APPROACH FOR MITIGATING THE FERRANTI EFFECT THROUGH OPTIMAL SELECTION AND PLACEMENT OF SHUNT REACTORS IN LONG-DISTANCE TRANSMISSION LINES // Журнал «Вестник науки» от 12 октября 2025 г. № 10 (91) том 2. С. 664 - 680. 2025 г. ISSN 2712-8849 // Электронный ресурс: https://www.вестник-науки.рф/article/25938 (дата обращения: 29.11.2026 г.)
Альтернативная ссылка латинскими символами: vestnik-nauki.com/article/25938
Нашли грубую ошибку (плагиат, фальсифицированные данные или иные нарушения научно-издательской этики) ?
- напишите письмо в редакцию журнала: zhurnal@vestnik-nauki.com